AQW 27242/22-27 Written question to the Minister of Education

To ask the Minister of Education whether he will increase the priority level applied to the minor works project to deliver a multi-purpose hall for St Francis' Primary, Drumaroad, to reflect that the modular unit housing the dining facility may need replaced.

Asked by Nick Mathison MLA on 16 May 2025

  • Answered
  • Written
Tabled
16 May 2025
Answer due by
3 June 2025
Answered
28 May 202512 days after tabling
Department
Department of Education
Priority question
No

Answer

The minor works scheme at St Francis’ Primary School is currently considered a Priority Three scheme i.e. curriculum based minor works scheme.

Given the design work, vesting of land and planning approval required for this project, it is being progressed to pre-tender stage. These stages would be required regardless of the prioritisation of the scheme. A decision to release to tender will be taken based on the prioritisation and the budget available at that time.