AQW 9566/22-27 Written question to the Minister of Education
To ask the Minister of Education to detail the estimated timeline for (i) completion of the construction of the Strule Shared Campus site; and (ii) the opening of all the schools on the site to receive pupils.
Asked by Nick Mathison MLA on 8 April 2024
- Answered
- Written
- Tabled
- 8 April 2024
- Answer due by
- 23 April 2024
- Answered
- 15 April 20247 days after tabling
- Department
- Department of Education
- Priority question
- No
Answer
My officials are finalising work on the Full Business Case for the Programme and a potential contractor is in place. On the current programme timeline, subject to all necessary approvals being in place, contract award is planned for Summer 2024.
Assuming successful appointment of a main works contractor and following the pre-construction design period, construction would then begin on site late 2024 with completion currently estimated as late 2027.
Custom and practice is that schools do not normally move to a new site mid-academic year which may mean that full campus opening could be September 2028.